ե֭

Construction

Fri November 01 2024

Related Information

Costain fined for rebar frame collapse

3 Feb 15 Costain and one of its concrete subcontractors have been fined after a frame of reinforcing steel toppled at a site in Birmingham, knocking two workers from their scissor-lift platforms.

The toppled scissor lifts at Frankley water treatment works
The toppled scissor lifts at Frankley water treatment works

Bell Formwork Services Ltd had been subcontracted by Costain Ltd to build the metal frame for a concrete tank at a new pumping station and water treatment site at Frankley water treatment works.

Birmingham Magistrates’ Court heard that two steel fixers, a 65-year-old man from Brownhills, Walsall, and a 45-year-old from Cheslyn Hay, Staffordshire, had been raised nearly five metres above ground in separate scissor-lifts to take measurements of the tank wall.

Shortly afterwards the wall of reinforcing bar collapsed, bending over in a wave-like motion, knocking over both scissor-lifts with the operators still inside.

The 65-year-old steel fixer remained in his platform as it landed on its side and crashed into a nearby support frame. He suffered bruising and pain in his leg and shoulder. His colleague was propelled from his platform as it landed on its side against a nearby support frame. He also escaped with just bruising, however.

An investigation by the Health & Safety Executive (HSE) into the incident on 12th November 2012 found that the steel reinforcement for the tank walls, 21m long and 6.3m high, was unstable due to its size, the slenderness of the steel bars and the weight of the steel at a high level. A temporary support should have been put in place every seven metres.  However, on the day only two support frames were used at 8.3-metre spacing, leaving a section of eight metres unsupported.

HSE found that Costain had not planned, managed or monitored the work properly, despite having suffered a similar collapse at another site earlier that year.

Bell Formwork Services failed to ensure that all practicable steps had been taken to prevent danger to persons, to ensure the reinforcement did not collapse. They did not take reasonable steps to prevent the collapse of the wall and failed to identify that support was inadequate because there was no managerial level supervision or monitoring during these early stages of the work.

Related Information

Costain Ltd of Vanwell Business Park, Maidenhead, Berkshire, pleaded guilty to breaching the ե֭ (Design and Management) Regulations 2007, and was fined £15,000 and ordered to pay costs of £1,980.

Bell Formwork Services Ltd of Pinchbeck Road, Spalding, pleaded guilty to a separate breach of the same regulations and was fined £15,000 and ordered to pay £1,851 costs.

HSE inspector Luke Messenger said after the hearing: “This was a serious incident and considering the size and weight of the wall, and the height from which the scissor-lifts overturned, it is extremely fortunate that no serious or even fatal injuries occurred.

“ե֭ and related companies need to ensure that the same degree of care and attention is given to the design and construction of temporary structures as it is to the design and construction of permanent works. Everything must be properly planned so it can be carried out safely by their staff.

“Both companies were experienced in their industry and should have done better.”

Got a story? Email news@theconstructionindex.co.uk

MPU

Click here to view latest construction news »