The project entails the strip out and refresh back to Cat “A” of five floors totalling 30,356 sq ft over a 10 week programme, with 5,511 sq ft required to be handed over within six weeks.
The works include the replacement of floors and ceilings as well as the renewal and replacement of mechanical and electrical services to the floors being renovated. Extensive common parts works will also be undertaken along with the refurbishment of toilet facilities on all floors together with the main fire escape staircases.